Ontario Power Generation reports 2009 first
quarter financial results
TORONTO, May 22 / Ontario Power Generation Inc. ("OPG" or
the
"Company")
today reported its financial and operating results for the three
months
ended March 31, 2009. Net loss for the first quarter of 2009 was $9
million
compared to net income of $162 million for the same period in 2008.
"OPG's results were significantly affected by a reduction in
electricity
generation,
higher fuel prices, and an increase in expenses related to planned
maintenance
outages at our nuclear generating stations," said President and
CEO
Jim Hankinson.
Total electricity generated in the first quarter of 2009 of 25.6
terawatt
hours
("TWh") was 13 percent lower than the first quarter 2008
production of
29.4
TWh. Nuclear production decreased by 1.0 TWh primarily as a result of
planned
maintenance outages. Hydroelectric production of 9.0 TWh was
marginally
lower than production of 9.1 TWh during the first quarter 2008.
Electricity
production from OPG's fossil stations decreased to 4.3 TWh
compared
to 7.0 TWh in the first quarter of 2008, primarily due to lower
electricity
demand as a result of Ontario's contracting economy, an increase
in
electricity production from other Ontario generators, and a significant
reduction
in natural gas prices compared to the cost of coal, which resulted
in
a displacement of coal-fired production.
OPG's Darlington nuclear generating station continued to achieve
exceptional
reliability with a unit capability factor of 99.9 percent in the
first
quarter of 2009. The Pickering A nuclear generating station had a unit
capability
factor of 42.4 percent primarily due to planned outage maintenance
work.
The unit capability factor of 84.9 percent for the Pickering B nuclear
station
was marginally lower than in the first quarter of 2008. The
availability
of OPG's regulated and unregulated hydroelectric generating
stations
remained at historically high levels. As a result of CO(2) emission
limits,
the operating profile of the coal-fired generating stations has
changed.
The reliability of OPG's fossil stations, now measured during the
peak
demand periods of January and February, and July and August, improved
over
the first quarter of 2008.
Income before interest and income taxes from OPG's electricity
generating
segments
of $243 million in the first quarter of 2009 decreased from $381
million
for the three months ended March 31, 2008. Gross margin decreased as a
result
of lower fossil and nuclear generation, higher fuel costs, and lower
non-electricity
generation revenue. The unfavourable impact of these factors
was
partially offset by higher electricity sales prices reflecting the Ontario
Energy
Board's ("OEB") rate decision for OPG's regulated hydroelectric
and
nuclear
facilities, and revenues related to the contingency support agreement
for
the Nanticoke and Lambton generating stations.
Operations, Maintenance and Administration expenses increased by
$51
million
in the first quarter of 2009, compared to the same quarter in 2008.
The
increase was primarily due to an increase in planned outage and
maintenance
activities at OPG's nuclear generating stations.
A loss before interest and income taxes of $164 million in the
Regulated
-
Nuclear Waste Management segment for the three months ended March 31, 2009
was
an improvement over the $185 million loss before interest and income taxes
in
the first quarter of 2008. The loss before interest and income taxes in
the
first
quarter of 2009 primarily resulted from reductions in the Ontario
Consumer
Price Index, which negatively affected the guaranteed return on the
Used
Fuel Fund, and lower returns on the Decommissioning Fund. This loss was
partially
mitigated by the establishment by the OEB of a regulatory variance
account
associated with the stations leased to Bruce Power, since a portion of
the
losses from the Used Fuel and Decommissioning Segregated Funds are related
to
these stations.
During the first quarter of 2009, OPG advanced on a number of new
generation
projects aimed at significantly contributing to Ontario's long-term
electricity
supply requirements:
Nuclear
- The Province
has announced that OPG will operate a new two-unit
nuclear power plant at the Darlington site. Proposal submissions
from
all three respondents were received by Infrastructure Ontario at
the
end of February. It is expected that a preferred vendor will be
selected by Infrastructure Ontario in the late spring of 2009. OPG
has initiated activities related to an environmental assessment and
licensing requirements.
Hydroelectric
- With respect
to the Niagara tunnel project, at March 31, 2009, the
tunnel boring machine had advanced to 3,794 metres, which
represents
37 percent of the tunnel length. It is now operating on a revised
alignment that will minimize remaining excavation in the Queenston
shale formation. OPG and the contractor are renegotiating the
design
build contract with a revised target cost and schedule. The
contract
includes incentives related to achieving the target cost and
schedule. The original project cost was estimated at $985 million
with a scheduled completion of June 2010, as approved by OPG's
Board
of Directors. The revised project cost is estimated at $1.6 billion
and the revised schedule targets completion by December 2013.
This
contract is expected to be finalized during the second quarter of
2009.
- The Lac Seul
generating station was declared in-service in February
2009 and has a capacity of 12.5 MW. OPG entered into a partnership
agreement with the Lac Seul First Nations ("LSFN")
regarding this
facility. OPG will have a 75 percent interest in the station, while
the LSFN will have a 25 percent interest.
- Project
financing was completed for the Upper Mattagami and Hound
Chute development projects in May 2009. Senior Notes totaling
$200 million were issued by the UMH Energy Partnership, a general
partnership between OPG and UMH Energy Inc., a wholly-owned
subsidiary of OPG.
Natural Gas
- The Portlands
Energy Centre ("PEC") is a 550 MW high-efficiency,
combined cycle, natural gas generation plant designed to meet
downtown Toronto's need for electricity. PEC is a limited
partnership
between OPG and TransCanada Energy Ltd. PEC was declared in-service
in a combined cycle mode in April 2009, earlier than the
contractual
in-service date of June 2009.
FINANCIAL AND OPERATIONAL HIGHLIGHTS
-------------------------------------------------------------------------
Three Months Ended
March
31
(millions of dollars - except where noted)
2009
2008
-------------------------------------------------------------------------
Earnings
Revenue after revenue limit rebate
1,481
1,563
Fuel expense
261
304
-------------------------------------------------------------------------
Gross margin
1,220
1,259
Operations, maintenance and administration expense
742
691
Depreciation and amortization
178
175
Accretion on fixed asset removal and nuclear
waste management liabilities
159 135
Losses on nuclear fixed
asset removal and
nuclear waste management funds
6
51
Other net expenses
26
13
-------------------------------------------------------------------------
Income before interest and income taxes
109
194
Net interest expense
39
40
Income tax expenses (recoveries)
79
(8)
-------------------------------------------------------------------------
Net (loss) income
(9)
162
-------------------------------------------------------------------------
Cash flow
Cash flow provided by operating activities
41
245
-------------------------------------------------------------------------
Income (loss) before interest and income taxes
Generating segments
243
381
Nuclear Waste Management segment
(164)
(185)
Other segment
30 (2)
-------------------------------------------------------------------------
Total income before interest and income taxes
109
194
-------------------------------------------------------------------------
Electricity generation (TWh)
Regulated - Nuclear
12.3
13.3
Regulated - Hydroelectric
4.7
4.6
Unregulated - Hydroelectric
4.3
4.5
Unregulated - Fossil-Fuelled
4.3
7.0
-------------------------------------------------------------------------
Total electricity generation
25.6
29.4
-------------------------------------------------------------------------
Average electricity sales price
(cents/kWh)
Regulated - Nuclear
5.5
4.9
Regulated - Hydroelectric
3.6
3.6
Unregulated - Hydroelectric
4.4
4.7
Unregulated - Fossil-Fuelled
4.8
4.8
OPG average sales price
4.8
4.7
Nuclear unit capability factor (percent)
Darlington
99.9
98.9
Pickering A
42.4
77.6
Pickering B
84.9
86.5
Equivalent forced outage rate - Peak (percent)
Unregulated- Fossil-Fuelled
15.8
18.6
Availability (percent)
Regulated - Hydroelectric
94.2
93.4
Unregulated- Hydroelectric
95.5
95.7
-------------------------------------------------------------------------
-------------------------------------------------------------------------
Ontario Power Generation Inc. is an Ontario-based electricity
generation
company
whose principal business is the generation and sale of electricity in
Ontario.
Our focus is on the efficient production and sale of electricity from
our
generation assets, while operating in a safe, open and environmentally
responsible
manner.
Ontario Power Generation Inc.'s unaudited consolidated financial
statements
and Management's Discussion and Analysis as at and for the three
months
ended March 31, 2009, can be accessed on OPG's Web site (www.opg.com),
the
Canadian Securities Administrators' Web site (www.sedar.com), or can be
requested
from the Company.
|